Question: Problem 1 2 - 3 3 ( LO . 3 ) David is the sole proprietor of a real estate construction business. The business uses

Problem 12-33(LO.3)
David is the sole proprietor of a real estate construction business. The business uses the
completed contract method on a particular contract that requires 16 months to complete.
The contract is for $500,000, with estimated costs of $300,000. At the end of 2020,
$180,000 of costs had been incurred. The contract is completed in 2021, with the total cost
being $295,000.
Determine the amount of adjustments for AMT purposes for 2020 and 2021.
For 2020, the AMT adjustment is
For 2021, the AMT adjustment is !
of $,x.
of $,x.
X .
Feedback
* Check My Work
 Problem 12-33(LO.3) David is the sole proprietor of a real estate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!