Question: Problem 1: (20 Points) Given the following network, with activity times in months. For each activity, the above number shows the activity number, and the

Problem 1: (20 Points) Given the following
Problem 1: (20 Points) Given the following network, with activity times in months. For each activity, the above number shows the activity number, and the number below shows the activity time, Activity number 3 Start 1 Activity time 5 3 (a) Please find the all of the paths. (b) Which path is the critical path? (6) How long is the project duration