Question: Problem 1 : ( 3 0 points ) A surveying team employed the differential leveling method to establish two temporary benchmarks, namely TBM 1 and

Problem 1: (30 points)
A surveying team employed the differential leveling method to establish two temporary
benchmarks, namely TBM1 and TBM2. They accomplished this by conducting a survey in a
closed-loop fashion, commencing from BM1, which had a known elevation, and subsequently
returning to BM1. Please construct and fill in the differential leveling table, concluding with an
arithmetic check. What is the discrepancy or error detected in this surveying process?