Question: Problem 1 : ( 3 0 ) Problem 2 : ( 3 0 ) The water engineer of a city's municipal department plans to build

Problem 1: (30) Problem 2: (30)
The water engineer of a city's municipal department plans to build a water tank to address the increasing
water demand of the city's fast-growing population. The available space for the tank (excluding access), is
600ft2. The planned inside depth of the tank is 10ft., and it is desired that its length is at least twice its
width (Length and width are outside dimensions). Space limitations dictate that the width cannot exceed
20ft. The tank will be built with reinforced concrete of 1ft. thickness (walls, base, and cover). The city
seeks to reduce the total cost of the concrete construction. The unit cost of concrete construction, which
includes not only concrete material costs but also formwork and other related costs, is
{:35.315ft3)
Find:
(a) Formulate the problem indicating decision variables, objective function, and constraints. (15)
(b) Solve the problem using Excel Solver and provide optimal tank dimension and cost. Round off tank
dimensions to the nearest 3''.(Hint: Use GRG Nonlinear solving method and initial non-zero
decision variable values)(15) Problem 3: (30)
A project manager is faced with assigning three separate projects amongst four (4) different profit
centers. The weekly profit/person (p) between the profit center and the projects varies because of the
distance and efficiency of each profit center. The available/required staffing for each profit center and
project are shown below. The project manager wishes to maximize total weekly profits.
Find:
a) Formulate the above problem as linear program optimization model with Network Diagram,
Objectives, Decision Variables, Constraints. Determine optimal assignments of persons (p) from
each profit center to each project and maximum weekly profits using Excel Solver. (Note: General
Mathematical Expressions of the Linear Programming Model are acceptable)(15)
b) Conduct a post-optimization sensitivity analysis using Excel Solver and answer the following
questions. (15)
i. Are all profit centers fully utilized? If not, which one is underutilized?
ii. Which profit center could contribute the most increase in weekly profit by increasing
available staff?
iii. Which assignments are sensitive to any decrease in profits?
A contractor has found natural reserves of sand and gravel at Bloomingdale and Valley Springs where he
may purchase such material. The net profit (markup), including delivery from Bloomingdale and Valley
Springs, is $2 and $3 per m3, respectively. After the material is brought to the site, it is mixed thoroughly
and uniformly, and the contract specifications state that the mix should contain a minimum of 30% sand.
A maximum total volume of 100,000m3 of mixed material is estimated for the project. The Bloomingdale
Pit contains 25% sand, and the Valley Springs Pit contains 50% sand. Total volume of material taken from
the Valley Spring pit must not exceed 60% of the total volume from Bloomingdale. As the new
construction engineer on the project, you are asked to determine how much material should be taken
from each pit to maximize profit.
Find: Using graphical methods only
a) Formulate the problem with mathematical expressions for decision variables, objective function,
and constraints. (10)
b) Solve the problem and determine the optimal volume of material transported from each pit as
well as the maximum expected profit. (10)
c) Perform post-optimization sensitivity analysis and provide range of optimality of objective
function coefficients and shadow price (Dual Value) for each constraint limit.(10)
Solutions to the following problems must include screen shots of formulated problems in Excel Solver.
 Problem 1: (30) Problem 2: (30) The water engineer of a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!