Question: Problem 1 3 - 1 8 ( Static ) Develop a material requirements plan for component H . Lead times for the end item and

Problem 13-18(Static)
Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2.(Leave no cells blank - be certain to enter "0" wherever required.)