Question: Problem 1 . 3 : A work group of 2 0 workers in a certain month produced 8 6 0 0 units of output working

Problem 1.3: A work group of 20 workers in a certain month produced 8600 units of output
working 8hr? day for 21 days. (a) What is the labor productivity ratio for this month? (b) In the next
month, the same worker group produced 8000 units but there were 22 workdays in the month and
the size of the work group was reduced to 14 workers. What is the labor productivity ratio for this
second month? (c) What is the productivity index using the first month as a base?
Problem 1.4: There are 20 forging presses in the forge shop of a small company. The shop
produces batches of forgings requiring a setup time of 3.0 hours for each production batch.
Average standard time for each part in a batch is 45 seconds, and there are an average of 600 parts
in a batch. The plant workforce consists of two workers per press, two foremen, plus three clerical
support staff. (a) Determine how many forged parts can be produced in 1 month, if there are 8
hours worked per day and an average of 21 days per month at one shift per day. (b) What is the
labor productivity ratio of the forge shop, expressed as parts per worker-hour?
Problem 2.1: If the normal time is 1.30 min for a repetitive task that produces one work unit per
cycle, and the company uses a PFD allowance factor of 12%, determine (a) the standard time for
the task and (b) how many work units are produced in an 8-hour shift at standard performance.
Problem 2.6: A worker performs a repetitive assembly task at a workbench to assemble products.
Each product consists of 25 components. Various hand tools are used in the task. The standard
time for the work cycle is 7.45 min , based on using a PFD allowance factor of 15%. If the worker
completes 75 product units during an 8-hour shift, determine (a) the number of standard hours
accomplished and (b) worker efficiency. (c) If the worker took only one rest break, lasting 13 min ,
and experienced no other interruptions during the 8 hours of shift time, determine her worker
performance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!