Question: Problem 1 ( 3 POINTS ) ( a ) Given the network diagram of the activities, list the paths and their durations, identify the critical

Problem 1(3 POINTS)
(a) Given the network diagram of the activities, list the paths and their durations, identify the critical path, and calculate their ES, EF, LS, and LF values. Also, calculate their slack times. (2 points)
There are 5 paths in this network (Networks sent to you as a pdf file).
Note: Network posted on Canvas as a separate file. You may take a print-out of this (if you have a printer) or draw it by hand on a piece of paper (takes less than 5 minutes to draw it).
(b) If activity F is delayed by 3 days and if activity H is delayed by 5 days, by how many days would the entire project be delayed? Assume no other activity gets delayed. ((1)/(2) point)
(c) If activity A is delayed by 1 day and if activity B is delayed by 3 days, by how many days would the entire project be delayed? Assume no other activity gets delayed. ((1)/(2) point)
Note: Questions (b),(c) are not linked to one another. Problem 1 Network (the ES, EF, LS, LF based probiem)
Note: If you do not have access to a printer, you may have to draw this network carefully on a piece of paper. This will take you less than 5 minutes - but please copy everything correctly on a sheet of paper.
Hint: There are FIVE paths in this network (I am giving this information so that you minimize your errors).
Problem 1 ( 3 POINTS ) ( a ) Given the network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!