Question: Problem 1 [ 3 ] : You are the project manager, and you have three projects running at your site. Your responsibility is to supply

Problem 1[3]:
You are the project manager, and you have three projects running at your site. Your responsibility is to supply a concrete sample with required compressive strength of 6000 psi. You ordered your three workers to produce and test three different mix design. The 28-day compressive strength test results from 5 cylinders obtained by each worker (in psi) are:
Worker 1: 6500,6000,6500,8000,5100,5500
Worker 2: 6300,6000,5100,6500,5200,6500
Worker 3: 7500,5200,7100,5500,4500,7500
Q1: Calculate: mean, and standard deviation of each workers strength test results.
Q2: Which worker's concrete are you going to select?
1 of 5
Problem 1 [ 3 ] : You are the project manager,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!