Question: Problem 1 4 - 1 4 ( Static ) Given the BOM and the MPS for end item A , complete the MRP schedule for
Problem Static
Given the BOM and the MPS for end item A complete the MRP schedule for items A C D and E
Note: Leave no cells blank be certain to enter wherever required.
In the BOM, at the top is A week. Below it we have the following three. B weeks. C week. D weeks. Below C week are the following two. E week. F weeks. Below D weeks are the following three. E week. G week. H weeks.
MPS
Item
A:
Click here for the Excel Data File
Item A C D E
Lot size rule LL LL LL Multiples FOQ
Safety stock
Beginning inventory
Week scheduled receipts