Question: Problem 1 4 - 1 4 ( Static ) Given the BOM and the MPS for end item A , complete the MRP schedule for

Problem 14-14(Static)
Given the BOM and the MPS for end item A, complete the MRP schedule for items A, C, D, and E.
Note: Leave no cells blank - be certain to enter "0" wherever required.
In the BOM, at the top is A,1 week. Below it we have the following three. B (1),3 weeks. C (4),1 week. D (2),2 weeks. Below C (4),1 week are the following two. E (2),1 week. F (6),2 weeks. Below D (2),2 weeks are the following three. E (4),1 week. G (4),1 week. H (1),3 weeks.
MPS
Item 12345678
A: 602050120100508040
Click here for the Excel Data File
Item A C D E
Lot size rule L4L L4L L4L Multiples FOQ =500
Safety stock 000100
Beginning inventory 000300
Week 1 scheduled receipts 6080401,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!