Question: Problem 1 : ( 4 5 points ) The time unit is day. ( Show your work ) table [ [ - Act,Pred,a ,

Problem 1: (45 points) The time unit is day. (Show your work)
\table[[-Act,Pred,a,m,b,Exp t,Var,ES,EF,LS,LF,Slack,If Crash,Crash $,C. rate,Crash by,$],[A,-,10,15,19,,,,,,,,0,0,,,],[B,-,19,25,28,,,,,,,,5,1000,,,],[C,A,18,18,18,,,,,,,,4,1600,,,],[D,A, B,7,13,19,,,,,,,,3,1800,,,],[E,B,16,18,20,,,,,,,,3,900,,,],[F,D,15,19,22,,,,,,,,2,800,,,],[G,E, F,14,20,26,,,,,,,,5,2500,,,]]
Draw AON network with ES, EF, LS, LF; Fill the table; Show Critical path;
What is the expected project completion time and what probability to complete it in exactly such time?
What is the project completion standard deviation and variance?
Crash the project to 5 days down.
Give the duration of project with 99% probability.
What is the probability of finishing the project in less than 80 days?
Problem 1 : ( 4 5 points ) The time unit is day.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!