Question: Problem 1 : ( 4 5 points ) The time unit is day. ( Show your work ) table [ [ - Act,Pred,a ,
Problem : points The time unit is day. Show your work
tableAct,Pred,ambExp tVar,ESEFLSLFSlack,If Crash,Crash $C rate,Crash by$ABCADA BEBFDGE F
Draw AON network with ES EF LS LF; Fill the table; Show Critical path;
What is the expected project completion time and what probability to complete it in exactly such time?
What is the project completion standard deviation and variance?
Crash the project to days down.
Give the duration of project with probability.
What is the probability of finishing the project in less than days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
