Question: Problem 1 4 - 9 ( Static ) Compute the takt time for a service system that intended to perform a standardized service. The system

Problem 14-9(Static)
Compute the takt time for a service system that intended to perform a standardized service. The system will have a total work time of 440 minutes per day, excluding two 10-minute breaks and an hour for lunch. The service system must process 90 jobs a day.