Question: Problem 1 6 - 1 2 ( Algo ) Your company assembles five different models of a motor scooter that is sold in specialty stores

Problem 16-12(Algo)
Your company assembles five different models of a motor scooter that is sold in specialty stores in the United States. The company uses the same engine for all five models. You have been given the assignment of choosing a supplier for these engines for the coming year. Due to the size of your warehouse and other administrative restrictions, you must order the engines in lot sizes of 1,040 each. Because of the unique characteristics of the engine, special tooling is needed during the manufacturing process for which you agree to reimburse the supplier. Your assistant has obtained quotes from two reliable engine suppliers and you need to decide which to use. The following data have been collected:
Requirements (annual forecast)12,480 units
Weight per engine 25 pounds
Order processing cost $ 215 per order
Inventory carry cost 20 percent of the average value of inventory per year
Note: Assume that half of the lot size is in inventory, on average (1,040-: 2=520 units).
Two qualified suppliers have submitted the following quotations:
ORDER QUANTITY SUPPLIER 1 UNIT PRICE SUPPLIER 2 UNIT PRICE
1 to 1,499 units/order $556 $554
1,500 to 2,999 units/order 552554
3,000+ units/order 550548
Tooling costs $25,900 $22,000
Distance 115 miles 100 miles
Your assistant has obtained the following freight rates from your carrier:
Truckload (42,000 pounds each load): $0.80 per ton-mile
Less than truckload: $1.20 per ton-mile
Note: Per ton-mile =2,000 pounds per mile
a-1. Calculate the total cost for each supplier.
Note: Round your answers to the nearest whole number.
a-2. Which supplier would you select?
multiple choice 1
Supplier 2
Supplier 1
b-1. If you could move the lot size up to ship in truckload quantities, calculate the total cost for each supplier.
Note: Do not round intermediate calculations. Round "Required lot size for truckload" and final answers to the nearest whole number.
HINT: Use (full) truckload cost rates and the lowest (feasible) unit cost for all calculations. For example, if there are 8.3 orders per year, dont split the 8.3 orders into 8 full truckloads and 0.3 less than truckloads - use the full truckload rate for all 8.3 orders. For annual purchase cost, dont use two different unit costs for the 8 complete orders and the 0.3 partial orders use the lowest (feasible) unit cost for all 8.3 purchase orders based on the lot size needed for a full truckload.
b-2. Would your supplier selection change?
multiple choice 2
Yes
No

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!