Question: Problem 1 6 - 1 7 ( Static ) Given the following information on job times and due dates. Job Job Time ( Hours )

Problem 16-17(Static)
Given the following information on job times and due dates.
Job Job Time
(Hours) Due Date
(Hours)
a 3.57
b 2.06
c 4.518
d 5.022
e 2.54
f 6.020
Click here for the Excel Data File
a-1. Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio.Sequence for First come, first served a-b-c-d-e-f
Sequence for Shortest processing time b-e-a-c-d-f
Sequence for Earliest due date e-b-a-c-f-d
Sequence for Critical ratio e-a-b-f-c-dFirst Come, First Served Shortest Processing Time Earliest Due Date Critical Ratio
Average flow time
Average job tardiness

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!