Question: Problem 1 7 - 1 2 ( Static ) A project manager has compiled a list of major activities that will be required to install
Problem Static
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
Use Table B and Table B
Activity Immediate
Predecessor Estimated Times
weeks
A
D A
E D
H E
F A
G F
B
I B
J I
K J
C
M C
N M
O N
End H G K O