Question: Problem 1 7 : On January 1 , 2 0 2 1 , Entity A started the construction of a building contract can be estimated
Problem : On January Entity A started the construction of a building contract can be estimated reliably. The project was completed on December
which resulted to penalty amounting to The entity provided the following
data concerning the direct costs related to the said project for and :
What is the construction revenue for the year ended December
a P
c P
b P
d P
What is the realized gross profit for the year ended December
a
c P
b P
d
What is the balance of construction in progress on December
a P
c
b P
d P
with a fixed contract price of P The outcome of the construction project
can be estimated reliably and the contractor decided to employ cost to cost method.
The following data are provided by the accountant and project manager concerning
the construction costs for the three years of construction:
What is the balance of Construction in Progress on December
a P
l
b P
d
Problem : On January Liquid Company accepted a longterm
construction project for an initial contract price of P to be completed on
June On January the contract price was increased to P
by reason of change in the design of the project. The outcome of the construction
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
