Question: Problem 1 9 : In 2 0 2 0 , Samsung entered into an agreement to construct a Building Problem 2 1 : GGDL Construction
Problem : In Samsung entered into an agreement to construct a Building Problem : GGDL Construction Corp. recently acquired the P Corp. P Corp has
incomplete accounting records. On one particular project, only the information
below is available:
P Corp uses the percentage of completion method and percentage of work
completed is determined through surveys of work performed engineers estimates
The cost incurred in is
a P
c P
b
d
at a contract price of P Construction data were as follows:
How much is the collection for the year
a P
c
b P
d P
Problem : In PBC Corp. was contracted to build PIPE for P million. The
project to be completed in two years and the contract provided for:
mobilization fee to be deducted from the last billing payable within
days after the assigning of the contract.
retention proyision on all billings
And payment of progress billing within days from acceptance.
PBC uses the percentage of completion method of accounting, estimated a gross
margin on the project. By the end of PBC had presented progress billings
corresponding to completion. All of the progress billings presented in were
accepted, except the last one for which was accepted on January With
the exception of one bill for which was due on January all of the billings
accepted in were settled. Payments made by PIPE in amounted to:
a P
c P
b P
d P
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
