Question: Problem 1 . A completely mixed high - rate activated sludge plant is to treat 1 5 , 0 0 0 m 3 d of

Problem 1.
A completely mixed high-rate activated sludge plant is to treat 15,000m3d of industrial wastewater. The primary effluent going to the activated sludge reactor has a BOD5 of 1100mgL that must be reduced to 150mgL prior to discharge to a municipal sewer. The flow diagram of the plant is given in the following Figure. Pilot plant analysis gave the following results: mean solid residence time =5d, MLSS concentration in the area tank =6000mgL VSS,Y=0.7kgkg,kd=0.03d-1.
Determine the following:
a. The hydraulic retention time and volume of the activated sludge reactor. (10 points)
b. The volumetric loading rate in kgBODsm3-d to the reactor. (10 points)
c. The FM ratio in the reactor. (10 points)
d. The mass (kgd) and volume (m3d) of solids wasted each day, at a waste solids concentration xw=12,000mgL.(10 points)
e. The sludge recirculation ratio (QrQ).(10 points
Problem 1 . A completely mixed high - rate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!