Question: Problem 1 . A concreting project for 1 0 0 service entrance posts in a subdivision is to be carried out. Using the plan shown

Problem 1. A concreting project for 100 service entrance posts in a subdivision is to be carried out. Using
the plan shown below. Determine the following:
41-45. The total volume of excavation.
46-50. The total volume of backfill.
51-60. The total volume of concrete.
61-65. The total number of 40-kg bag cement, quantity of sand and gravel in cu.m. Consider class B
concrete mixture. (Note: Round-up your answer to nearest whole number)