Question: Problem 1 A new solid - fluid processing unit will be built as an extension to an existing refinery. It will produce 4 0 tons

Problem 1 A new solid-fluid processing unit will be built as an extension to an existing refinery. It will produce 40 tons of product per day. Your company has data from a similar process that was built in 2009 at another refinery. The following figure presents the equipment cost for such a unit in 2009.
a) Estimate the equipment cost in December 2022.
b) Estimate the capital cost for this process in December 2022.
Problem 2. Determine the cost in August 2023 of a steam methane reformer unit with capacity 40kgs.