Question: PROBLEM # 1 : A production manager needs to develop a production schedule to meet the following demand: Period 1 2 3 4 Demand 5

PROBLEM #1: A production manager needs to develop a production schedule to meet the following demand:
Period
1
2
3
4
Demand
500
1300
1600
500
production costs are as follows:
production cost during regular time: $4 per unit
cost of subcontracting: $5 per unit
Inventory carrying cost = $3 per unit per period
Back-order costs = $8 per unit per period.
Regular production rate: 900 units per period
You can subcontract at the rate of 150 units per period only during the second and third periods. Develop a production schedule for this scenario and answer the following questions.
Equation: Surplus/Shortage in any period = Quantity Produced + Quantity Subcontracted Demand
What is the average inventory for the first period?
What is the surplus or shortage in the second period?
What is the inventory at the beginning of the second period?
What is the average inventory for the second period?
What is the surplus or shortage in the third p
What is the total cost of the items subcontracted during periods 2 and 3 together?
What is the total cost of the backlog for all he four periods together?
What is the total cost of the backlog for all the four periods together?
What is the total cost of meeting the demand for the four periods is (Note: you have to add all the costs):

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!