Question: Problem 1 Chapter 7: Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed
Problem 1
Chapter 7: Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed before the next Joint Commission survey in 18 weeks. Project activity times are listed in the table below.
- Draw the network diagram and identify the project paths.
- What is the project completion time and total project costs if only normal times are used?
- Determine the minimum cost-schedule for this project.
- What is the difference in total project costs between the earliest completion time of the project using normal times and the minimum cost-schedule you derived in part b?
| Activity | Immediate Predecessors | Normal Time (NT) (weeks) | Normal Cost (NC) ($) | Crash Time (CT) (weeks) | Crash Cost (CC) ($) |
| A | --- | 6 | $600 | 2 | $1,400 |
| B | A | 7 | $200 | 3 | $600 |
| C | --- | 9 | $500 | 6 | $950 |
| D | C | 2 | $800 | 1 | $1,200 |
| E | D | 8 | $1,600 | 5 | $2,800 |
| F | B, D | 5 | $200 | 4 | $400 |
| G | F | 4 | $400 | 3 | $750 |