Question: Problem 1 Given the following information, determine: a. How many workers are needed? (1 point) b. What is the takt time? (1 point) C. How
Problem 1 Given the following information, determine: a. How many workers are needed? (1 point) b. What is the takt time? (1 point) C. How many workers are needed at each station? (1 point) d. What is the daily production? (1 point) Operation 1 2 3 4 5 6 Demand rate is 500 parts in 8 hours Efficiency = 87% Standard Time (min.) 3.5 2.5 5.0 1.5 4.0 2.0