Question: Problem # 1 Jenny Malone works for the Columbus based Cummins Diesel Engine company. Jenny works in the production scheduling department and she is developing

Problem #1
Jenny Malone works for the Columbus based Cummins Diesel Engine company. Jenny works in the production scheduling department and she is developing an MRP planning schedule for Item J. Please assist Jenny by developing the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. The lead time is one week. (Leave no cells blank - be certain to enter "0" in all open cells as required.)
WEEK NUMBER
ITEM J 012345
Gross requirements 664161
On hand 44
Net requirements
Planned order receipt
Planned order release
Period 12345
Item J
LT =1
Q = L4L Gross requirements 664161
Scheduled receipts
0
0
0
0
0
Projected available balance
44
0
0
0
0
Net requirements
0
22
0
41
61
Planned order receipts
0
22
0
41
61
Planned order releases
22
0
66
82
0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!