Question: Problem 1 On July 1 , 2 0 2 4 , Forward Corporation purchased a parcel of land as a factory site for $ 5

Problem 1
On July 1,2024, Forward Corporation purchased a parcel of land as a factory site for $525,000. An old building on the property was demolished and construction began on a new warehouse that was completed on October 15,2024. Costs incurred on the construction project are listed below.
Cost of building construction.
Title insurance.
Cost of constructing a driveway
Legal fees to purchase land.
Architect's fees q,
Cost of demolishing the old building q,
Proceeds from salvaged materials from building demolition.
Delinquent property taxes, January 1- June 30,2023
Interest during construction on the construction loan.
Cost of parking lot and fencing. q,
Cost of grading and filling the land. q,
Excavation costs. q,
Required:
Determine the cost of the land, the building and the land improvements. Please show your work for partial credit.
Problem 1 On July 1 , 2 0 2 4 , Forward

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!