Question: Problem 1 The following details are available regarding a project: Determine the critical path, the critical activities and the project completion time? Tasks Precedence Time

Problem 1

The following details are available regarding a project:

Determine the critical path, the critical activities and the project completion time?

Tasks Precedence Time
a - 6 Weeks
b - 4 Weeks
c a 3 Weeks
d b 4 Weeks
e b 3 Weeks
f - 10 Weeks
g e, f 3 Weeks
h c, d 2 Weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts