Question: Problem 1 The following details are available regarding a project: Determine the critical path, the critical activities and the project completion time? Tasks Precedence Time
Problem 1
The following details are available regarding a project:
Determine the critical path, the critical activities and the project completion time?
| Tasks | Precedence | Time |
| a | - | 6 Weeks |
| b | - | 4 Weeks |
| c | a | 3 Weeks |
| d | b | 4 Weeks |
| e | b | 3 Weeks |
| f | - | 10 Weeks |
| g | e, f | 3 Weeks |
| h | c, d | 2 Weeks |