Question: Problem 1 The following precedence diagram reflects three time estimates in weeks for each activity. Determine: a. The expected completion time for each path and

Problem 1 The following precedence diagram

Problem 1 The following precedence diagram reflects three time estimates in weeks for each activity. Determine: a. The expected completion time for each path and its variance. b. The probability that the project will require more than 49 weeks. The probability that the project can be completed in 46 weeks or less. c. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 8-8-8 5-6-7 9-9-9 1 2 4 13-13-13 10.5-13-15.5 10 7 10-12-14 10-11-12 7-10-12 5 9

Step by Step Solution

There are 3 Steps involved in it