Question: Problem 1 : The MOE has requested that your company provide results from water samples taken on three non - consecutive days at a location
Problem : The MOE has requested that your company provide results from water samples taken on three nonconsecutive
days at a location m downstream of the discharge location. Your team has identified the following tasks:
Visit the sampling location site to determine if there are any barriers to sampling.
Order sampling equipment.
Take three samples with at least one day in between each.
Send samples out for analysis.
Receive report back from analysis company.
Meet with the team to discuss results.
Meet with MOE to report results.
Create a Gantt Chart to show illustrate a proposed timeline for this project. State any necessary assumptions.