Question: Problem 1 : This problem compares RM and EDF schedules. Consider two tasks with periods p _ ( 1 ) = 2 and p _
Problem : This problem compares RM and EDF schedules. Consider two tasks with
periods p and p and execution times ee Assume that the
deadline for each execution is the end of the period.
a Give the RM schedule for this task set and find the processor utilization. How does
this utilization compare to the Liu and Layland utilization bound?
b Show that any increase in e or e makes the RM schedule infeasible. If you hold
ee and p constant, is it possible to reduce p below and still get a
feasible schedule? By how much? If you hold ee and p constant, is
it possible to reduce p below and still get a feasible schedule? By how much?
c Increase the execution time of task to be e and give an EDF schedule. Is
it feasible? What is the processor utilization?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock