Question: Problem # 1: Your Company is constructing a high rise hotel building in Makkah for a total cost of SR 250 MM. The original work

Problem # 1: Your Company is constructing a high
Problem # 1: Your Company is constructing a high rise hotel building in Makkah for a total cost of SR 250 MM. The original work supposed to finish today (April 6, 2020). Due to the 24 hours curfew, all work stopped. All project records are kept in the site and no one can access the site. You need to calculate the cost overrun. The project manager told you that they have completed 2/3 of the work and the cost-schedule index is 0.49. Use the available information to calculate the cost overrun