Question: Problem 10-09 (Algorithmic) The Ace Manufacturing Company has orders for three similar products: Product Order (Units) A 1750 B 500 C 1100 Three machines are

Problem 10-09 (Algorithmic)

The Ace Manufacturing Company has orders for three similar products:

Product

Order (Units)

A

1750

B

500

C

1100

Three machines are available for the manufacturing operations. All three machines can produce all the products at the same production rate. However, due to varying defect percentages of each product on each machine, the unit costs of the products vary depending on the machine used. Machine capacities for the next week and the unit costs are as follows:

Machine

Capacity (Units)

1

1550

2

1450

3

1150

Product

Machine

A

B

C

1

$0.80

$1.30

$0.70

2

$1.40

$1.30

$1.50

3

$0.80

$0.80

$1.20

Use the transportation model to develop the minimum cost production schedule for the products and machines. Show the linear programming formulation. If required, round your answers to one decimal place.

The linear programming formulation and optimal solution are shown.

Let

x1A

Units of product A on machine 1

x1B

=

Units of product B on machine 1

x3C

=

Units of product C on machine 3

Min

...x1A

+

...x1B

+

...x1C

+

...x2A

+

...x2B

+

...x2C

+

...x3A

+

...x3B

+

...x3C

s.t.

...x1A

+

...x1B

+

...x1C

...

...x2A

+

...x2B

+

...x2C

...

...x3A

+

...x3B

+

...x3C

...

...x1A

+

...x2A

+

+

...x3A

=

...

...x1B

+

...x2B

+

...x3B

=

...

...x1C

+

...x2C

+

...x3C

=

...

xij 0 for all i, j

Optimal Solution

Units

Cost

1-A

1-B

1-C

2-A

2-B

2-C

3-A

3-B

3-C

Total $

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!