Question: Problem 10-13 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3] Koontz Company manufactures a number of products. The standards relating

Problem 10-13 Basic Variance Analysis; the Impact of Variances on Unit Costs [LO10-1, LO10-2, LO10-3]

Koontz Company manufactures a number of products. The standards relating to one of these products

are shown below, along with actual cost data for May.

Standard Cost per UnitActual Cost per Unit Direct materials: Standard: 1.80 feet at $2.40 per foot$ 4.32 Actual: 1.75 feet at $2.60 per foot$ 4.55 Direct labor: Standard: 0.90 hours at $16.00 per hour14.40 Actual: 0.95 hours at $15.40 per hour14.63 Variable overhead: Standard: 0.90 hours at $4.00 per hour3.60 Actual: 0.95 hours at $3.60 per hour3.42 Total cost per unit$22.32$22.60 Excess of actual cost over standard cost per unit$0.28

The production superintendent was pleased when he saw this report and commented: "This $0.28 excess cost is well within the 2 percent limit management has set for acceptable variances. It's obvious that there's not much to worry about with this product."

Actual production for the month was 12,000 units. Variable overhead cost is assigned to products on the basis of direct labor-hours. There were no beginning or ending inventories of materials.

Required:1.Compute the following variances for May:a.Materials price and quantity variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).)

b.Labor rate and efficiency variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).)

c.

Variable overhead rate and efficiency variances. (Input all amounts as positive values. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e, zero variance).)

2.How much of the $0.28 excess unit cost is traceable to each of the variances computed in (1) above. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your answers to 2 decimal places.)

3.How much of the $0.28 excess unit cost is traceable to apparent inefficient use of labor time? (Input all values as positive amounts. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Do not round intermediate calculations. Round your final answers to 2 decimal places.)

rev: 07_28_2016_QC_CS-56149

rev: 10_28_2014_QC_57647, 10_30_2014_QC_57529, 11_01_2014_QC_57647, 11_03_2014_QC_57647, 06_13_2016_QC_CS-53459

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!