Question: Problem 10.17 Blossom Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses

Problem 10.17 Blossom Mills management is evaluating two alternative heating systems. Costs and projected energy savings are given in the following table. The firm uses 11.5 percent to discount such project cash flows. Year ON M7 System 100 -$1,345,900 261,710 406,130 597,740 881,800 System 200 $1,695,900 574,300 530,900 454,100 336,900 What is the NPV of the systems? (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors and intermediate calculations. Round final answers to 0 decimal places, e.g. 5,275.) NPV of system 100 ist $ NPV of system 200 is Which system should be chosen? Blossom should choos Click if you would lil System 200 neither system System 100 this question: Open Show Work