Question: Problem 10.5 At Maggard Micro Manufacturing, Inc., workers press semiconductors into predrilled slots on printed circuit boards. The elemental motions for normal time used by

Problem 10.5 At Maggard Micro Manufacturing, Inc., workers press semiconductors into predrilled slots on printed circuit boards. The elemental motions for normal time used by the company:r are as follow: Reach 6 inches for semiconductors 4U TMU Grasp the semiconductor 1C! TMU Move semiconductor to printed circuit board 3G TMU Position semiconductor 35 TMU Press semiconductor into slots 65 TMU Move board aside 2G TMU (Each time measurement unit is equal to [1.0006 min.) Determine the normal time for this operation in minutes and in seconds
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock