Question: Problem 10-6 Scenario Analysis (LO2) The most likely outcomes for a particular project are estimated as follows: Unit price: $48 Variable cost: $23 Fixed cost:
Problem 10-6 Scenario Analysis (LO2)
| The most likely outcomes for a particular project are estimated as follows: |
| Unit price: | $48 | |
| Variable cost: | $23 | |
| Fixed cost: | $305,000 | |
| Expected sales: | 29,100 units per year | |
| However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 14 years and requires an initial investment of $0.95 million, which will be depreciated straight-line over the project life to a final value of zero. The firm's tax rate is 35% and the required rate of return is 14%. What is project NPV in the "best case" scenario, that is, assuming all variables take on the best possible value? (Round your answer to the nearest whole dollar amount.) | |
| NPV in the "best case" scenario | $ |
| What about the "worst case" scenario? (Round your answer to the nearest whole dollar amount.) | |
| NPV in the "worst case" scenario | $ |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts