Question: Problem 11-1 NPV Project K costs $75,000, its expected cash inflows are $15,000 per year for 11 years, and its WACC is 13%. What is
Problem 11-1 NPV
Project K costs $75,000, its expected cash inflows are $15,000 per year for 11 years, and its WACC is 13%. What is the project's NPV?