Question: Problem 13-2 Rev The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C
Problem 13-2 Rev
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
| Item | End | B | C | D | E | F | G | H |
| LT (week) | 1 | 3 | 1 | 1 | 1 | 1 | 1 | 1 |
| Amount on hand | 0 | 7 | 12 | 22 | 8 | 29 | 5 | 0 |
Click here for the Excel Data File
Note: If you click the Hint link on the left you can watch a walk-through of the problem using different numbers.
a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: It will be easier to work through this if you redraw the BOM and add in the information on leadtime and how many units of each are in stock.)
b. An order for the end item is scheduled to be shipped at the start of week 15. What is the latest week that the order can be started and still be ready to ship on time? (Hint: Find the longest leadtime path in the product (also called cumulative leadtime) and then subtract it from 15.)