Question: Problem 14-5 (Algo) Based on the BOM shown below, 5 weeks B (4) 3.3 weeks C(2) 3.3 weeks D (3) 3 weeks D (4) 3

Problem 14-5 (Algo) Based on the BOM shown below,

Problem 14-5 (Algo) Based on the BOM shown below, 5 weeks B (4) 3.3 weeks C(2) 3.3 weeks D (3) 3 weeks D (4) 3 weeks G (3) 3 weeks F (3) 4 weeks E (3) 3 weeks F(3) 4 weeks E (3) 3 weeks F (3) 4 weeks What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks