Question: Problem 15 Intro Your company is considering two projects and has estimated the following cash flows Year Project A Project B -15,000 20,000 10,000 10,000
Problem 15 Intro Your company is considering two projects and has estimated the following cash flows Year Project A Project B -15,000 20,000 10,000 10,000 10,000 20,000 B Part 1 Attempt 1/10 for 10 pts of project B expands your manufacturing capacity by building a separate factory, what is the relevant cash flow for evaluating project B in year 2? 0+ decimals Submit Part 2 B - Attempt 1/10 for 10 pts. If project B replaces an existing factory (project A), what is the relevant cash flow for evaluating project B in year 2? 0decimals Submit Part 3 B Attempt 1/10 for 10 pts. if project replaces an existing factory (project A), what is the relevant cash flow for evaluating project B in year 0? 0+ decimals Submit