Question: Problem 15.19 Question Help a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are

Problem 15.19 Question Help a) Using the FCFS

Problem 15.19 Question Help a) Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: The following jobs are waiting to be processed at Julie Morel's machine center. Sequence Job 1 Date Job Received Job 115 A B Due Date Duration (days 185 17 195 20 180 14 200 22 205 16 122 120 118 125 D E All dates are according to shop calendar days. Today on the planning calendar is day 130, and none of the jobs have been started or scheduled. Compute all times based on initiating work on day 130