Question: Problem 15-9 (Algo) Given the following project network Tank Tak Tisk weeks Task Tak a-1. Identify the critical path. OA-CEF O A-B-D-F OA-C-D-F a-2. Identify

Problem 15-9 (Algo) Given the following project
Problem 15-9 (Algo) Given the following project
Problem 15-9 (Algo) Given the following project network Tank Tak Tisk weeks Task Tak a-1. Identify the critical path. OA-CEF O A-B-D-F OA-C-D-F a-2. Identify the earliest start and finish for each task (Leave no cells blank.be certain to enter "0" wherever required.) Earliest Start Immediate Predecessors None weeks B A Earliest Completion weeks weeks weeks weeks A D E B.c C IDE woes weeks weeks weeks F weeks OA-GE.F O A-B-D-F OA-C-D-F -2. Identify the earliest start and finish for each task. (leave no cells blank - be certain to enter *o" wherever required) Eartiest Start Earliest Completion B Immediate Predecessor None A A B, C O, E weeks weeks weeks mo weeks weeks weeks weeks weeks weeks weeks F weeks b. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "0" wherever required.) Task Latest Completion Latest Start Slack Immediate Successors None F F mm D, E D Next >

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!