Question: Problem 16-72 (Algo) Variance Computations with Missing Data (LO 16-5, 6) The following information is provided to assist you in evaluating the performance of the

Problem 16-72 (Algo) Variance Computations with Missing Data (LO 16-5, 6) The following information is provided to assist you in evaluating the performance of the production operations of Studio Company 47,000 $130,680 110,880 160,380 Units produced (actual) Master production budget Direct materials Direct labor Overhead Standard costs per unit Direct materials Direct labor Variable overhead Actual costs Direct materials purchased and used Direct labor Overhead $1.65 * 2 gallons per unit of output $14 per hour x 0.2 hour per unit $11.50 per direct labor-hour 5134,050 (76,600 gallons) 120,781 (0,980 hours) 167,200 (61% is variable) Variable overhead is applied on the basis of direct labor-hours Required: Calculate all variable production cost price and efficiency variances and fixed production cost price and production volume variances (Do not round intermediate calculations. Indicate the effect of each variance by selecting "P" for favorable, or "U" for unfavorable. if there is no effect, do not select elther option.) Required: Calculate all variable production cost price and efficiency variances and fixed production cost price and production volume variances (Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.) Price Variance Efficiency Variance Production Volume Variance Direct materials Direct labor Variable overhead Fored overhead
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
