Question: Problem 16-9 (Static) A wholesale grocery distribution center uses a two-step process to fill orders. Tomorrow's work will consist of filling the seven orders shown.

Problem 16-9 (Static) A wholesale grocery

Problem 16-9 (Static) A wholesale grocery distribution center uses a two-step process to fill orders. Tomorrow's work will consist of filling the seven orders shown. Determine a job sequence that will minimize the time required to fill the orders. Order B C D E F G TIME (hours) Step 1 Step 2 1.20 1.40 0.90 1.30 2.00 0.80 1.70 1.50 1.60 1.80 2.20 1.75 1.30 1.40 Click here for the Excel Data File Sequence Order 1 2 3 4 5 6 7