Question: Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the

Problem 17-7

Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. UseTable B.

TIME IN DAYS

Activity Immediate Predecessor Optimistic Most Likely Pessimistic
A 5 6 7
B 8 8 11
C A 6 8 11
D 9 12 15
E C 5 6 9
F D 5 6 7
G F 2 3 7
H B 4 4 5
I H 5 7 8
End E, G, I

b.

What is the probability that the project can be completed in 24 days or less? In 21 days or less?(Round your teand z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.)

Days Probability
24 days or less
21 days or less

c.

Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.(Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.)

Probability
Day 24
Day 21

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!