Question: Problem 17-7 Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the
Problem 17-7
| Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. UseTable B. |
| TIME IN DAYS | ||||
| Activity | Immediate Predecessor | Optimistic | Most Likely | Pessimistic |
| A | 5 | 6 | 7 | |
| B | 8 | 8 | 11 | |
| C | A | 6 | 8 | 11 |
| D | 9 | 12 | 15 | |
| E | C | 5 | 6 | 9 |
| F | D | 5 | 6 | 7 |
| G | F | 2 | 3 | 7 |
| H | B | 4 | 4 | 5 |
| I | H | 5 | 7 | 8 |
| End | E, G, I |
| b. | What is the probability that the project can be completed in 24 days or less? In 21 days or less?(Round your teand z values to 2 decimal places and "Standard deviation" to 3 decimal places. Round your final answers to 4 decimal places.) |
| Days | Probability |
| 24 days or less | |
| 21 days or less |
| c. | Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.(Round your intermediate calculations to 3 decimal places and final answers to 4 decimal places.) |
| Probability | |
| Day 24 | |
| Day 21 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts