Question: Problem 2 1 - 2 1 ( Algo ) The MRP gross requirements for Item X are shown here for the next 1 0 weeks.

Problem 21-21(Algo) The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $13. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. The MRP gross requirements for Item \( X \) are shown here for the next 10 weeks. Lead time for \( A \) is two weeks, and setup cost is \(\$ 13\) There is a carrying cost of \(\$ 0.02\) per unit per week. Beginning inventory is 75 units. Use the least total cost lot-sizing method to determine when and for what quantity the first order should be released.

Step by Step Solution