Question: Problem 2 . ( 2 0 points ) Excelsior Springs Ltd . schedules production of one end product, Hi - Sulphur, in batches of 8
Problem points
Excelsior Springs Ltd schedules production of one end product, HiSulphur, in batches of units whenever the projected ending inventory balance in a quarter falls below units. It takes one quarter to make a batch of units. Excelsior currently has units on hand. The sales forecast for the next four quarters is:
Quarter
Forecast
a Prepare a timephased MPS record showing the sales forecast and MPS for HiSulphur.
b What are the inventory balances at the end of each quarter?
c During the first quarter, no units were sold. The revised forecast for the rest of the year is:
Quarter
Forecast
How does the MPS change?