Question: Problem 2 2 - 1 1 ( Static ) Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising

Problem 22-11(Static)
Bill Edstrom, managing partner at a biomedical consulting firm, has requested your expert advice in devising the best schedule for the following consulting projects, starting at the beginning of the day on February 2.
The consulting firm charges a flat rate of $4,000 per day. All four firms impose fines for lateness. Reardon Biotech charges a $500-perday fine for each day that the completion of the consulting work is past the due date; Vertex Pharmaceuticals, Novartis, and OSI Pharmaceuticals all charge a fine of $1,500 per day for each day late.
Prepare alternative schedules based on the following priority rules: SOT, FCFS, EDD, STR, and another rule-longest processing time (LPT), which orders jobs according to longest assigned first, second longest assigned second, and so on. For the sake of simplicity, assume that consulting work is performed seven days a week.
a. Calculate the total costs (sum of the late fines) for each rule.
\table[[Priority Rules,Costs],[SOT,],[FCFS,],[EDD,],[STR,],[LPT,]]
 Problem 22-11(Static) Bill Edstrom, managing partner at a biomedical consulting firm,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!