Question: Problem 2 ( 20 points): A facility in Houston was cost estimated at $12106 with production of capacity of 560,000 unit in 2012. What would
Problem 2 ( 20 points): A facility in Houston was cost estimated at $12106 with production of capacity of 560,000 unit in 2012. What would be the estimated cost of this plant in 2023, if the capacity index is 1.37 and cost index is 5.37 for production of 1.7106 unit