Question: Problem 2 3 points An assembly line is to operate eight hours per day with a desired output of 400 units per day. The following

Problem 2 3 points An assembly line is to operate

Problem 2 3 points An assembly line is to operate eight hours per day with a desired output of 400 units per day. The following table contains information on this product's task times and precedence relationships Activity A B C D E F G H a b Task Time (Seconds) 60 80 20 50 90 30 30 60 Immediate Predecessor A A A B, C C, D E, F G a. What is the workstation cycle time required to produce 300 units per day? b. Is it feasible for the assembly line to meet their desired output? Why or why not