Question: Problem 2 (4.0 pts.) Consider the BOM below. End Item Item A (3) 1 week Item B (2) 2 weeks Item C (1) 3 weeks

Problem 2 (4.0 pts.) Consider the BOM below. End

Problem 2 (4.0 pts.) Consider the BOM below. End Item Item A (3) 1 week Item B (2) 2 weeks Item C (1) 3 weeks Item D (2) 2 weeks Item E (1) 2 weeks Item B (2) 2 weeks Item E (1) 2 week Item F (2) 1 week The forecasted demand and scheduled receipts for End Item is shown in the table below. Currently, there are no on-hand inventory. Week Demand Scheduled Receipts 11 100 12 90 30 13 90 14 100 30 15 120 16 110 30 17 90 (2a) Create an MPS for the End Item