Question: Problem 2 : A project manager has compiled a list of major activities that will be required to install a heating system. The list includes

Problem 2: A project manager has compiled a list of major activities that will be required to install a heating system. The list includes three-point estimates of durations (optimistic, most likely, pessimistic) for activities and the precedence relationships.
What is the estimated expected time for project completion
Time Estimates (days)
Activity Immediate
Predecessor(s) Optimistic Most Likely Pessimistic
Start -
A Start 385062
B Start 9099108
C Start 85100115
D A 192531
E B 91100115
F D 626568
End C, E, F
What is the estimated expected time for project completion
 Problem 2: A project manager has compiled a list of major

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!