Question: Problem 2 : A project manager has compiled a list of major activities that will be required to install a heating system. The list includes
Problem : A project manager has compiled a list of major activities that will be required to install a heating system. The list includes threepoint estimates of durations optimistic most likely, pessimistic for activities and the precedence relationships.
What is the estimated expected time for project completion
Time Estimates days
Activity Immediate
Predecessors Optimistic Most Likely Pessimistic
Start
A Start
B Start
C Start
D A
E B
F D
End C E F
What is the estimated expected time for project completion